STEPS:

  1. Site preparation, clearing, setting the final elevation.
  2. Excavation  to proper depths.
  3. Craft the bottom as a mirror image of the fiberglass pool bottom.
  4. Compact the bottom base to accept the pool shell.
  5. Hoist the fiberglass shell into the prepared hole with a crane.
  6. Level the pool shell.
  7. Plumbing lines are in place ready to be connected at the appointed time.
  8. Lock shell in place by alternatively backfilling with sand washed in  with a water wand, and by filling the pool with water.
  9. Once the pool is locked into place and the backfill carefully compacted, the water filled shell is allowed to recirculate for a few days.
  10. Coping and deck are then installed.
  • Pool Chemistry Guidelines

    Increase your knowledge of pH, alkalinity, free chlorine, combined chlorine, calcium hardness, and cyanuric acid.

    Click on this link for your
    Free Pool Chemistry Guide,
    compliments of Anchor Design & Pool.

  • Affiliations

    Powered by ServiceMagic
    The Association of Pool & Spa Professionals
    Bioguard
    Vyn-All Pool Products

Beautiful Pools

At Anchor Pools we have designed, built, and maintained many wonderful gunite, vinyl and fiberglass pools over the years. Visit our Gallery to view some of our work.

Ask Thom

Here's the latest tip from Anchor Design & Pool President Thom Kearns:
Think Spring